XTX Markets brings its 22.5-megawatt Finnish data centre online

A data centre building in a Finnish landscape, representing XTX Markets' Kajaani campus
Photo by Hert Niks on Pexels

XTX Markets has begun operating its first company-owned data centre in Kajaani, Finland, on 24 November 2026. The London-based trading firm says delays in permits for electricity lines could affect further investment at the site.

Grid capacity shapes the buildout

Electricity and grid connections currently cover two buildings on the 193-hectare campus. A third facility is being built for delivery in mid-2028, but its power supply is not guaranteed.

The 22.5 megawatts now in operation amount to 9% of XTX Markets' 250-megawatt ambition, which emerged in April 2024, according to Finance Magnates' calculation. The company has spent more than €400 million (about $465 million) on construction, mostly with Finnish contractors. That is roughly 40% of the more than €1 billion it set aside for the site in January 2025.

Money is not the constraint cited by the firm. For 2025, its three UK entities together recorded net revenue of £3.93 billion (about $5.3 billion), a 43% increase on the previous year. Their profit after tax was £1.71 billion.

Permits and migration shape delivery

Mike Irwin, chief operating officer at XTX Markets, identified permits to expropriate land for power lines as a growing obstacle. He said approvals that used to take months can now take years. Irwin also said bureaucracy and limited engagement put plans for billions more in investment at risk. XTX would contribute financially to infrastructure, he said, but future spending decisions depend on greater engagement.

Finnish public broadcaster Yle reported that XTX plans five data centres along the Kajaani River and could build faster with sufficient power. Three of the planned five therefore rely on electricity that has not been secured. The permit warning and site details were also reported by Finance Magnates.

XTX says it has completed its storage move from a rented data centre five kilometers away. In one six-week period, the firm transferred 417 petabytes on 385 servers, involving roughly 17,000 drives with a combined weight of 26 metric tons. The second building is due to start operating in 2027.

What to watch next

For infrastructure teams, the immediate checks are whether each build phase has an assigned power supply, which land and line permits remain outstanding, and what date XTX expects power to reach the third facility. The report gives no connection timetable for that building.

The account also does not specify how computing workloads will be distributed between buildings or what utilisation the initial 22.5 megawatts supports. Operators assessing similar projects should track how power delivery, building commissioning and storage plans align.